Massachusetts
Working at the Cabot hydroelectric generating station, owned by FirstLight Power Resources, TRC completed engineering services to replace the entire plant’s protective relay equipment.
Between October 2018 and June 2019, our electrical engineers replaced the original existing electromechanical protective relays with state-of-the-art Schweitzer Engineering Laboratories (SEL) microprocessor relays. The relay replacements covered the hydro station’s six generators (including stator ground protection), two station buses, generator step-up transformer and the station service transformer.
We provided all the necessary design drawings to complete the project at the facility and provided protective relay settings and proper relay coordination for all the new relays that were installed, including detailed setting basis documents, relay setting calculations, and relay setting file development.
As a result, the station’s aging electromechanical relays was upgraded with modern digital protection relays, increasing flexibility, security and reliability, while reducing required maintenance activities.
Related Projects
Site Design and Permitting – Virginia Military Institute Aquatic Center
TRC supported the permitting and compliance required to build a new 58,000 square foot Aquatic Center.
Transmission Project Environmental Assessments and Permitting
Strengthening the reliability of the downstate New York power grid
- Electric Utilities
- Electrical and Power Engineering
- Environmental Assessment, Permitting and Compliance
Mohican-Battenkill Transmission Line Rebuild and Reconductoring
TRC is providing environmental and agricultural inspection support
Chapin Beach Coastal Resilience Improvements
Protecting the roadway from erosion and storm damage.
Bayonne Energy Center Project & Submarine Cable
TRC supports the development of a 512 MW electric generating facility on a brownfield site and a 6.5-mile submarine electric …
Sharing Our Perspectives
Our practitioners share their insights and perspectives on the trends and challenges shaping the market.
Webinar Replay: Substation Automation – Best Practices for IEC 61850 Implementation
March 29, 2022
Modernizing utility equipment, standards and processes pays dividends for improved safety, security and reliability. But transitioning to a new high-tech system model can be challenging.
The Best Process for Transforming Thermal Generation Power Plants
February 9, 2022
Faced with an aging fleet, stricter environmental regulations, reduced costs for natural gas and competition from renewables, more than 600 power plants have been decommissioned in the last 20 years, a pace that will increase with the announced closure of nearly 350 additional plants by 2025.
Amplifying the Next Phase of Fleet Electrification: The Pickup
September 30, 2021
TRC’s analysis for one client fleet shows that even a $70,000 EV can compete on cost with a comparable gas-hybrid vehicle priced at $40,000 – at least in California where upfront and ongoing incentives stack up quickly.
TRC Acquires Montreal’s Quatric, Expanding Digital Capabilities for Utilities
June 16, 2021
Today, TRC announced the expansion of its digital capabilities with the acquisition of Quatric, a Montreal, QC and Quincy, MA-based firm that provides engineering services and technology solutions to electric and gas utilities.
NERC Addresses Single Points of Failure in Protection Systems Among Other FERC Concerns
October 25, 2018
Under the proposed NERC TPL-001-5 standard, utilities with transmission planning responsibilities will be required to identify reliability risks related to protection system failures and take mandatory corrective action. It will be critical to have an in depth understanding of your company’s protection system settings and to perform the system studies necessary to identify where single points of failure may result in cascading tripping of transmission elements. Mitigation actions may require the installation of redundant protection systems which in turn may lead to significant substation redesign. Transmission planners and planning coordinators should begin preparing for any necessary protection system changes. TPL-001-5 Overview NERC began studying the reliability risk associated with single points of protection system failure starting in 2011 as directed in FERC Order 754. TPL-001-5 will bring significant changes for Planning Coordinators and Transmission Planners as they perform annual Planning Assessments. There is a new obligation to adequately account for the reliability risk posed by single point of protection system failure via risk-based Assessment. This reliability risk management approach will be implemented through modifications to the Category P5 Planning Event which is described in Table 1 of the TPL-001-5 standard. NERC believes that the most cost-effective Corrective Action Plans to address unacceptable system performance for the P5 Planning Events will likely be to add protection system component redundancy in certain cases. Protection system redundancy changes to address Category P5 Event system performance violations should reduce or even negate non-redundant component related risks that need to be considered in assessing transmission system performance. These risks will be identified during simulations of certain extreme events as required under the standard. TPL-001-5 also addresses reliability risks related to outage management as directed in FERC Order 786. The standard requires utility planners to consider maintenance outages of significant facilities as well as outages for critical long lead time to repair or replace equipment. Specifically, it addresses stability analysis to assess system performance for conditions expected during possible unavailability of long lead time equipment. Although it is not a NERC defined term, it is believed that a “spare equipment strategy will be sufficient to allow flexibility for utilities to conduct both steady state and stability analysis required by TPL-001-5. For example, a utility’s spare equipment strategy may include the warehousing of a replacement transformer to be installed given the failure of an in service transformer. When a utility’s spare equipment strategy may prevent major transmission equipment from being out-of-service for one year or more, this possible equipment unavailability need not be assessed as part of TPL-001-5.
TRC Expands Presence in Power Market with Acquisition of Ohio-based IJUS
October 1, 2018
LOWELL, Mass. – TRC, a leading provider of end-to-end engineering, consulting and construction management solutions fueled by innovative technology, announced today it has acquired IJUS, a top power/utility engineering firm based in Gahanna, Ohio. Terms of the deal were not disclosed.
TRC and partners win $1 million grant for engineering innovative New York microgrid
April 20, 2017
TRC is proud to support Huntington, NY bolster power reliability and climate-change resiliency with a sophisticated new “community microgrid’’ combining solar energy, a fuel cell, biogas and traditional natural gas to deliver electricity and heat to local customers and institutions.
Download Whitepaper: 10 Years of Insights for Clean Community Microgrids
March 1, 2023
Clean, community microgrids represent a promising and timely opportunity for you to advance your customer offering and deliver meaningful societal benefits, all while modernizing your grid and providing you with load flexibility.
Start Your Batteries: Mass Fleet Electrification is Coming (And What We Can do to Prepare)
April 13, 2022
As we plan for and make early investments for fleets, we’ll be paving the way for higher degrees of market penetration of passenger vehicles and other modes of transportation as well.
Ensuring a Just Transition: Optimizing Opportunities for All in the Low-Carbon Future
January 24, 2022
Carbon elimination of the magnitude needed to address climate change requires systems-level change that can only be reached by incremental, ground-up progress, building upon what we have achieved thus far.
10 Takeaways from the COP26 Climate Meeting
November 17, 2021
There are compelling reasons to be optimistic about the outcomes of the COP26 meeting. Notably, agreement among all nations that more needs to be done, by both private and governmental bodies, to contain and mitigate climate change.
Amplifying the Next Phase of Fleet Electrification: The Pickup
September 30, 2021
TRC’s analysis for one client fleet shows that even a $70,000 EV can compete on cost with a comparable gas-hybrid vehicle priced at $40,000 – at least in California where upfront and ongoing incentives stack up quickly.
TRC Acquires New Jersey’s Clean Energy Program Contract and Assumes Program Administrator Role
January 17, 2021
NEW BRUNSWICK, NJ and LOWELL, MA. – Jan. 17, 2017 – TRC Companies Inc., a recognized leader in engineering, environmental consulting and construction-management services, today announced it has acquired the contract to serve as Program Administrator of New Jersey’s Clean Energy Program™ (NJCEP), which has provided more than $300 million annually in support to homeowners, businesses…