Our technology, engineering and field services are supporting our client to supply 1.4 BCF of natural gas to a LNG export facility via a 64 mile 36” pipeline with one midpoint 50,000 HP compressor station.

We managed all aspects of the project including:

  • Required documentation and FERC filings
  • Early stage routing and constructability utilizing proprietary routing technology with field verification
  • Right of Way and land permission for preliminary and environmental surveys

The projected is expected to be in service in 2018.

By employing our routing technology, the client had a defensible route very early in the project life cycle. This facilitated permitting and reduced the time it would have taken via a traditional “desktop” study.